Burlington Northern Santa Fe (BNSF) will be conducting their 2020 Tie Gang project. Two years ago, BNSF modernized the schedule for Chicago Division Tie Gangs. Previously, these tie replacements would have been scheduled over 3 to 6 weeks. Now, the work should be completed in 4 nights. In this year’s project, BNSF will change out 11,000 ties on main track 3 utilizing roughly 40 pieces of specialized rail equipment and more than 175 workers.

Night work will be taking place between 9/17 and 9/20. During this time all trains passing the work zones will be required to sound their whistles. The Tie Gang will utilize large lighting racks for illuminating the work zone and their equipment can also be loud. In addition, several nightly crossing closures will be necessary. The crossing closures are listed below:

Friday, September 18 (7PM - 9AM)
Highlands Pedestrian Crossing - Closed
Park Pedestrain Crossing - Closed
Saturday, September 19 (7PM - 9AM)
Highlands Pedestrian Crossing - Closed
Park Pedestrian Crossing - Closed
Garfield - Open
Washington - Closed
Lincoln - Closed
Vine Pedestrian Crossing - Closed
Monroe - Open
Stough - Open